Acceptance report

Acceptance report Word-Vorlage

Project name

Classification Select an element.
Status Select an element.
Programme name
Project number
Project managerProject manager
Version0.1
Date Click here to enter a date.
ClientClient
Author/authors
Distributor

List of changes

VersionDateChangeAuthor
0.1

Table 1: Change control

Description

The acceptance report documents the fulfilment of the agreement on the product/system properties and existing defects. It is a legally binding document.

Subject of acceptance

Subject of acceptanceDescription
Software product xyApplication used in the xyz area

Table 2: Acceptance object

Acceptance participants

RoleName
Client / CustomerRolf Bühler
Project managerRoland Frey
SupplierPatrick Hoose

Table 3: Acceptance participation

Basics

DesignationVersion no. / designation / date
Offer30.12.2018

Table 4: Basics

Acceptance procedure

Text…….

Acceptance criteria with defect classes

The defects found or the unfulfilled requirements (expectations) are categorised in classes from 1 to 4. Class 0 is only used if a flawless result is to be reported separately:

No.Defect classesDescription
0flawlessFlawless and fulfils requirements
1insignificant defectUsage possible, usability is present, defects should nevertheless not occur
2minor defectUsage possible, usability is only slightly impaired
3serious defectUse is still possible, usability is severely impaired
4critical defectUnusable;
Essential functionality is not given;
Operation is not responsible (e.g. safety-related)

Table 5: Defect classes

The classification reflects the severity of the consequences and the effort required to rectify any defects that can be identified. The assignment of the identified defects to a defect class also roughly prioritises the order in which the defects are to be rectified.

If a defect class between 1-3 is achieved, the system/product can be accepted with reservations. However, measures must be defined to rectify the defects. A follow-up inspection is mandatory.

If, on the other hand, class 4 defects are identified, the system/product cannot be accepted and the contractor must take immediate measures to rectify these defects. The contractor must also arrange for a new acceptance test.

Delivery results and defects

Ref. no.Delivery result - description - requirementDefect descriptionDefect classMeasureResponsibleDeadline
01Customer management
Entry of new customers
Address is not saved correctly
saved correctly
3Defect correctionMüller15.06.2020

Table 6: Delivery results and defects

Acceptance event

☐The acceptance object was inspected without notification of defects. Acceptance is without reservation.

The acceptance object was inspected and accepted with reservations. The defects must be rectified within the specified period and the solution must be inspected again for acceptance.

The acceptance object has been inspected.
Acceptance is refused.

Signature

Name Function Place & date Signature

Abbreviations and glossary

Abbreviation / technical termExplanation
HERMESProcedure methodology for projects and programmes
HERMES 5 is an eCH standard

Table 7: Abbreviations and glossary